Ventilation Improvements in Schools

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$6.4M
$6,431,355
Federal share80%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2024
20232024
Built

Approved 2.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 6, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 20, 2022