Brock Trail improvements
Federal contribution
$156,319
Federal share60%
of $260.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 28, 2025
2023202420252026
Built
Approved 3.4 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Corporation of the City of Brockville
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Aug 1, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 6, 2022
- Construction end8 months lateforecast Nov 30, 2022
Also in Brockville
- Brockville Water Pollution Control Centre Upgrade$22.3M
- Construction of the Maritime Discovery Centre of the 1000 Islands (MDC)$5.7M
- HVAC, Bottle Water Filling Station, Portable, Retrofits, Wifi, Windows$5.2M
- Automatic Door Opener; Video Camera Childcare Project Group; Washroom Project Group; Site Project Group; HVAC Ventilation Upgrades$2.1M
- To replace aging HVAC Equipment and Controls.$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63587 in the federal list. How to read these figures.