Various Active Transportation Enhancements
Federal contribution
$503,480
Federal share60%
of $839.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 28, 2025
2023202420252026
Built
Approved 3.4 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Cobourg
- Construction start
- May 1, 2022(actual)
- Construction end
- Dec 31, 2025(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 1, 2022
- Construction end3 months earlyforecast Mar 31, 2026
Also in Cobourg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63600 in the federal list. How to read these figures.