Moose Jaw Trails & Pathways Master Plan, Province of Saskatchewan

Moose Jaw, Saskatchewan

completeCapacity BuildingATF
Federal contribution
$45,000
Federal share100%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2022
2023
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Moose Jaw
Construction start
Dec 2, 2022(actual)
Construction end
Sep 11, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Aug 1, 2022
  • Construction end5 months lateforecast Mar 31, 2023

Also in Moose Jaw

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63732 in the federal list. How to read these figures.