Sicamous Narrows AT Crossing Feasibility Study

Sicamous, British Columbia

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
2023
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Construction start
Jan 2, 2023(actual)
Construction end
May 28, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 26, 2022
  • Construction end3 months lateforecast Feb 28, 2023