Development of an Active Transportation Plan, Strategy and Design Concepts - Township Of Warwick, Province Of Ontario

Warwick, Ontario

approvedCapacity BuildingATF
Federal contribution
$26,000
Federal share68%

of $38.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 26, 2024
202320242025
BuiltForecast

Approved 2.4 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Township of Warwick
Construction start
May 23, 2022(forecast)
Construction end
Nov 28, 2022(forecast)

Also in Warwick

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63780 in the federal list. How to read these figures.