Installation of a Booster Pumping Station in North East Quadrant of Warwick Water Distribution System
Federal contribution
$335,174
Federal share45%
of $740.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Warwick
- Construction start
- May 1, 2017(actual)
- Construction end
- Feb 28, 2019(actual)
Against the original forecast
- Construction end9 months lateforecast May 31, 2018
Also in Warwick
- Replacement of Sunset Avenue, Confederation Line, and Victoria Street Watermains$1.2M
- Reconstruction of a Section of Victoria Street in the Town of Watford$210.4K
- COVID-19 Resilience for Watford Arena$80.0K
- Development of an Active Transportation Plan, Strategy and Design Concepts - Township Of Warwick, Province Of Ontario$26.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48928 in the federal list. How to read these figures.