completeCapacity BuildingATF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
2023202420252026
Built

Approved 2 years before the announcement.

Program
Active Transportation Fund
Construction start
Jul 26, 2022(actual)
Construction end
Jan 9, 2026(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2022
  • Construction end3.4 years lateforecast Sep 1, 2022