Pedestrian Connectivity Master Plan
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Didsbury
- Construction start
- Sep 29, 2022(actual)
- Construction end
- Mar 26, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2022
- Construction end10 months lateforecast May 31, 2023
Also in Didsbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63790 in the federal list. How to read these figures.