Pumphouse Upgrade

Didsbury, Alberta

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Didsbury
Construction start
Aug 1, 2018(actual)
Construction end
Jan 15, 2019(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 26, 2018
  • Construction end2 months earlyforecast Mar 31, 2019