Mobility study - Bicycle infrastructure on rue de Terrebonne between avenue Belmore and avenue Girouard in the Borough of Côte-des-Neiges-Notre-Dame-de-Grâce
Federal contribution
$50,000
Federal share30%
of $165.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 6, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Montréal
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Sep 1, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 1, 2022
- Construction end10 months lateforecast Nov 1, 2022
Also in Montréal