Replacement of a chiller at Cégep André-Laurendeau
Federal contribution
$144,940
Federal share27%
of $532.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep André-Laurendeau
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Nov 15, 2023(actual)
Against the original forecast
- Construction start7 months earlyforecast Feb 1, 2023
- Construction end5 months lateforecast Jun 30, 2023
Also in Montréal