Rehabilitation of biology classrooms at Cégep de Lévis
Federal contribution
$167,750
Federal share43%
of $392.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Lévis
- Construction start
- Sep 15, 2023(actual)
- Construction end
- Aug 16, 2024(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 15, 2024
Also in Lévis