Renovation of washrooms at the Gabrielle Roy Pavilion of Cégep de l'Outaouais
Federal contribution
$290,660
Federal share72%
of $404.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de l'Outaouais
- Construction start
- May 29, 2023(actual)
- Construction end
- Nov 3, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Aug 31, 2023