Repair of facades of École nationale d'administration publique
Federal contribution
$70,290
Federal share34%
of $208.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- École nationale d'administration publique
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Nov 4, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast May 2, 2022
- Construction end5 months lateforecast Jun 17, 2022
Also in Québec