Schedule

Announced and approvedSep 10, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Dec 1, 2022(actual)
Construction end
Apr 25, 2023(actual)

Against the original forecast

  • Construction end20 months earlyforecast Dec 15, 2024