Rehabilitation of the ventilation of the attics of the Georges-Cabana Pavilion of the Université de Sherbrooke

Sherbrooke, Quebec

completeVentilationCVRIS
Federal contribution
$211,381
Federal share45%

of $472.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2024
2024
Built

Approved 17 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Université de Sherbrooke
Construction start
May 29, 2023(actual)
Construction end
Dec 13, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 5, 2023
  • Construction end5 months lateforecast Jul 23, 2023