Back to projects

Renovation of lobbies and optimization of ventilation in the Faculty of Education of the Université de Sherbrooke

Sherbrooke, Quebec

completeVentilationCVRIS
Federal contribution
$321,573
Federal share22%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Université de Sherbrooke
Construction start
May 1, 2023(actual)
Construction end
Dec 14, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast Aug 31, 2023

Also in Sherbrooke

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63850 in the federal list. How to read these figures.