Rural Municipality of Keys No. 303, Gazdewich Bridge
Federal contribution
$68,335
Federal share17%
of $409.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2023
202320242025
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Keys No. 303
- Construction start
- Sep 1, 2024(actual)
- Construction end
- Jun 30, 2025(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2024
- Construction end9 months lateforecast Oct 1, 2024
Also in Keys No. 303
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63902 in the federal list. How to read these figures.