RM of Keys No. 303, Red Bin Road Bridge

Keys No. 303, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$67,903
Federal share17%

of $407.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2023
202320242025
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 12, 2024(actual)
Construction end
Jun 30, 2025(actual)

Against the original forecast

  • Construction end9 months lateforecast Oct 1, 2024