Construction of bus stops for the public transit service in the Mi'kmaw community of Eskasoni, Cape Breton, Nova Scotia
Federal contribution
$95,775
Federal share100%
of $95.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 29, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Eskasoni Transit Service Ltd.
- Construction start
- May 1, 2023(actual)
- Construction end
- Sep 26, 2024(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2022
- Construction end18 months lateforecast Mar 31, 2023
Also in Eskasoni
- New facility for the Unamaki Institute of Natural Resources (UINR) and Mikmaq Environmental Learning Center (MELC): Revitalizing Netukulimk$4.4M
- Purchase of vehicles and supporting infrastructure to provide transit service in the rural areas of the Cape Breton Regional Municipality, Nova Scotia$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63970 in the federal list. How to read these figures.