New facility for the Unamaki Institute of Natural Resources (UINR) and Mikmaq Environmental Learning Center (MELC): Revitalizing Netukulimk
Federal contribution
$4.4M
$4,419,253
Federal share100%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2022
2023202420252026
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Unama'ki Institute of Natural Resources
- Construction start
- Jun 1, 2024(actual)
- Construction end
- Dec 15, 2025(forecast)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2024
Also in Eskasoni
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64767 in the federal list. How to read these figures.