City of Greater Sudbury - Planning - Feasibility Study and Fleet Transition Plan
Federal contribution
$112,856
Federal share80%
of $141.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 22, 2022
202320242025
Built
Approved 5 months before the announcement.
- Program
- Zero Emission Transit Fund
- Ultimate recipient
- The City of Greater Sudbury
- Construction start
- Sep 22, 2022(actual)
- Construction end
- Dec 19, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 6, 2022
- Construction end8 months lateforecast Apr 30, 2024