Electric Bike Charging Stations
Federal contribution
$15,513
Federal share15%
of $101.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 5, 2025
202320242025
Built
Approved 2.4 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Tourisme Cantons-de-l'Est
- Construction start
- Jun 13, 2023(actual)
- Construction end
- Apr 4, 2025(actual)
Against the original forecast
- Construction end20 months lateforecast Aug 1, 2023
Also in Sherbrooke
- South bypass of the Sherbrooke agglomeration by extending Highway 410 - Phase II$35.6M
- Expansion of Cabana Operations Center$30.8M
- Acquisition of 40 electric buses$24.8M
- Multipurpose Centre at Bishop's University - Sherbrooke$13.2M
- Renovation of Sherbrooke, Deauville and Brompton water treatment plants$6.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64205 in the federal list. How to read these figures.