Shared street on boulevard Gouin Est in the borough of Ahuntsic-Cartierville

Montréal, Quebec

completeActive TransportationATF
Federal contribution
$1.6M
$1,584,000
Federal share60%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 20, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Montréal
Construction start
Jul 17, 2023(actual)
Construction end
Sep 24, 2025(actual)

Against the original forecast

  • Construction start13 months earlyforecast Aug 1, 2024
  • Construction end12 months lateforecast Oct 1, 2024