MacPherson Drive Link to Voyageur Cycle Route & Recreation Hub

East Ferris, Ontario

completeActive TransportationATF
Federal contribution
$962,665
Federal share56%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2024
2023202420252026
Built

Approved 19 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Municipality of East Ferris
Construction start
Apr 23, 2023(actual)
Construction end
Dec 1, 2025(actual)

Against the original forecast

  • Construction start12 months earlyforecast May 1, 2024
  • Construction end3 months lateforecast Sep 1, 2025

Also in East Ferris

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64292 in the federal list. How to read these figures.