Replacement and upgrading of a 20 metre stormwater culvert and rehabilitation of 4.3km of stormwater collection and conveyance system.
Federal contribution
$43,295
Federal share41%
of $106.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of East Ferris
- Construction start
- Aug 21, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 2, 2017
Also in East Ferris
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49286 in the federal list. How to read these figures.