CR2 - Brockville to Cardinal - Feasibility Study for the Implementation of Multi-use Pathways and/or Bike Lanes
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
BuiltForecast
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- United Counties of Leeds and Grenville
- Construction start
- May 2, 2022(forecast)
- Construction end
- Mar 31, 2023(forecast)
Also in Brockville
- Brockville Water Pollution Control Centre Upgrade$22.3M
- Construction of the Maritime Discovery Centre of the 1000 Islands (MDC)$5.7M
- HVAC, Bottle Water Filling Station, Portable, Retrofits, Wifi, Windows$5.2M
- Automatic Door Opener; Video Camera Childcare Project Group; Washroom Project Group; Site Project Group; HVAC Ventilation Upgrades$2.1M
- To replace aging HVAC Equipment and Controls.$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64378 in the federal list. How to read these figures.