Lawrence Heights Neighbourhood Mobility Plan
Federal contribution
$50,000
Federal share25%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
BuiltForecast
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 1, 2022(forecast)
- Construction end
- Apr 30, 2023(forecast)
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64405 in the federal list. How to read these figures.