Centennial College's Active Transportation Strategy
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2024
20232024
Built
Approved 21 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Centennial College
- Construction start
- Jan 15, 2023(actual)
- Construction end
- May 31, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Sep 1, 2022
- Construction end3 months lateforecast Mar 1, 2023