Safe Routes to Schools Strategy for the Municipality of the Kings
Federal contribution
$50,000
Federal share63%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 27, 2025
202320242025
BuiltForecast
Approved 2.7 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of the County of Kings
- Construction start
- Aug 1, 2022(forecast)
- Construction end
- Mar 30, 2023(forecast)