Lesser Slave Lake: Northshore Trail Phase 2 Planning/Design
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 20, 2023
2023
BuiltForecast
Approved 15 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Alberta TrailNet Society
- Construction start
- Jun 1, 2022(forecast)
- Construction end
- Nov 30, 2022(forecast)
Also in Edmonton