Integrated enhancement and rehabilitation of rest stops, rest areas and signage on the La Campagnarde bicycle path in Acton RCM, Montérégie, Quebec

Acton Vale, Quebec

completeActive TransportationATF
Federal contribution
$257,309
Federal share60%

of $428.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2025
202320242025
Built

Approved 2.3 years before the announcement.

Program
Active Transportation Fund
Construction start
Mar 17, 2024(actual)
Construction end
Jul 21, 2025(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 1, 2024
  • Construction end4 months earlyforecast Nov 15, 2025

Also in Acton Vale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64444 in the federal list. How to read these figures.