Chilkoot Way Active Transportation Improvements, Whitehorse, Yukon

Whitehorse, Yukon

completeActive TransportationATF
Federal contribution
$382,230
Federal share75%

of $509.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 25, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Whitehorse
Construction start
Aug 1, 2023(actual)
Construction end
Nov 14, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2023
  • Construction end4 weeks lateforecast Oct 15, 2024