Back to projects

West Toronto Railpath Extension, Province of Ontario

Toronto, Ontario

approvedActive TransportationATF
Federal contribution
$23.0M
$23,028,000
Federal share17%

of $132.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 1, 2024
2023202420252026
BuiltForecast

Approved 19 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Toronto
Construction start
Mar 20, 2023(forecast)
Construction end
Dec 30, 2025(forecast)

Also in Toronto