Active Transportation Plan for John Abbott College
Sainte-Anne-de-Bellevue, Quebec
Federal contribution
$50,000
Federal share98%
of $50.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 5, 2025
202320242025
BuiltForecast
Approved 2.5 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Cégep John Abbott
- Construction start
- Sep 19, 2022(forecast)
- Construction end
- Feb 17, 2023(forecast)
Also in Sainte-Anne-de-Bellevue