Active Transportation Street Team
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2022
20232024
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Jan 12, 2024(actual)
- Construction end
- Sep 30, 2024(actual)
Against the original forecast
- Construction start12 months lateforecast Jan 1, 2023
- Construction end3 months earlyforecast Dec 31, 2024
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64556 in the federal list. How to read these figures.