Back to projects

Active Transportation Street Team

Saskatoon, Saskatchewan

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2022
20232024
Built

Approved 6 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Saskatoon
Construction start
Jan 12, 2024(actual)
Construction end
Sep 30, 2024(actual)

Against the original forecast

  • Construction start12 months lateforecast Jan 1, 2023
  • Construction end3 months earlyforecast Dec 31, 2024