Creating Connections: Accessing the Harvest Moon Trail in Kings County, Nova Scotia
Federal contribution
$165,000
Federal share60%
of $275.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 27, 2025
today
20232024202520262027
BuiltForecast
Approved 2.2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of the County of Kings
- Construction start
- May 1, 2025(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start22 months lateforecast Jul 3, 2023
Also in Kings