Active Transportation Improvements Planning Study

Edmonton, Alberta

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share45%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2023
2023
Built

Approved 10 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Edmonton
Construction start
Jun 28, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2022
  • Construction end3 months lateforecast Dec 31, 2022

Also in Edmonton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64603 in the federal list. How to read these figures.