City of Barrie - Battery Electric Bus Pilot

Barrie, Ontario

completePublic TransitZETF
Federal contribution
$1.6M
$1,650,000
Federal share50%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 25, 2022
202320242025
Built

Approved 5 months before the announcement.

Program
Zero Emission Transit Fund
Construction start
Jul 6, 2022(actual)
Construction end
Apr 23, 2025(actual)

Against the original forecast

  • Construction end8 months earlyforecast Dec 31, 2025