Back to projects

St. Clare's Mercy Hospital - Integrated OR and Total Joint Arthroplasty

St. John's, Newfoundland and Labrador

completeHealthcare InfrastructureCVRIS
Federal contribution
$640,000
Federal share80%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2022(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction end4 months lateforecast Aug 1, 2023

Also in St. John's