Jeunesse au Soleil Community Centre
Federal contribution
$10.8M
$10,750,896
Federal share49%
of $21.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2022
2023202420252026
Built
Approved 3 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Sun Youth Organization
- Construction start
- Aug 26, 2024(actual)
- Construction end
- Feb 28, 2026(actual)
Against the original forecast
- Construction start15 months lateforecast May 18, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64796 in the federal list. How to read these figures.