Town of Orangeville - Planning - Feasibility Study and Fleet Transition Plan
Federal contribution
$83,280
Federal share80%
of $104.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2023
20232024
Built
Approved 12 months before the announcement.
- Program
- Zero Emission Transit Fund
- Ultimate recipient
- Town of Orangeville
- Construction start
- Mar 31, 2023(actual)
- Construction end
- Mar 25, 2024(actual)
Against the original forecast
- Construction start9 months lateforecast Jul 6, 2022
Also in Orangeville
- Dufferin County Administration and Provincial Offences Court Addition$2.7M
- Upgrading of the Water Pollution Control Plant$2.4M
- Rehabilitation of the West Sector Reservoir$2.0M
- Reconstruction of Roads and Services in the South Park and Village Green Subdivisions$1.6M
- New Transfer Terminal and Bus Acquisition$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64927 in the federal list. How to read these figures.