West End Community Centre Energy Retrofit - HVAC Upgrades: Equipment Right-Sizing, Energy Recovery and Air Source Heat Pumps
Federal contribution
$1.7M
$1,693,520
Federal share79%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2023
20222023
Built
Approved 11 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- The Corporation of the City of Guelph
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Mar 30, 2023(actual)
Against the original forecast
- Construction start8 months earlyforecast Nov 22, 2021
- Construction end10 months lateforecast May 31, 2022