Expansion of the theater hall of the Old Post Office
Federal contribution
$2.3M
$2,334,500
Federal share35%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 12, 2023
today
20232025202720292031
BuiltForecast
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Lévis
- Construction start
- Apr 4, 2029(forecast)
- Construction end
- Jun 3, 2031(forecast)
Also in Lévis