Street Reconstruction 2022 - Drake Avenue and Bartlett Avenue
Labrador City, Newfoundland and Labrador
Federal contribution
$606,009
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Labrador City
- Construction start
- Jul 7, 2023(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2023