NL English School District Headquarters Ventilation Upgrades
St. John's, Newfoundland and Labrador
Federal contribution
$76,010
Federal share80%
of $95.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Newfoundland and Labrador English School District
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Jul 31, 2024(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 15, 2022
- Construction end4 months lateforecast Mar 31, 2024