Glovertown Road Upgrades
Glovertown, Newfoundland and Labrador
Federal contribution
$157,359
Federal share33%
of $472.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Glovertown
- Construction start
- Jun 25, 2024(actual)
- Construction end
- Nov 6, 2024(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 2, 2024
- Construction end4 months lateforecast Jul 18, 2024
Also in Glovertown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65072 in the federal list. How to read these figures.