New Brunswick Museum - Construction Phase
Federal contribution
$49.9M
$49,900,000
Federal share46%
of $107.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 25, 2024
today
20242025202620272028
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- New Brunswick Museum
- Construction start
- Aug 18, 2025(actual)
- Construction end
- Jan 31, 2028(forecast)
Against the original forecast
- Construction start3 months lateforecast Jun 2, 2025