New Brunswick Museum - Construction Phase

Saint John, New Brunswick

underwayCultureGIS
Federal contribution
$49.9M
$49,900,000
Federal share46%

of $107.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 25, 2024
today
20242025202620272028
BuiltForecast

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
New Brunswick Museum
Construction start
Aug 18, 2025(actual)
Construction end
Jan 31, 2028(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jun 2, 2025

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65132 in the federal list. How to read these figures.