Back to projects

New Brunswick Community College -Saint John Campus Redevelopment

Saint John, New Brunswick

underwayGreen EnergyGIS
Federal contribution
$22.9M
$22,950,000
Federal share50%

of $45.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2022
today
2023202520272029
BuiltForecast
Program
Green Infrastructure Stream
Construction start
Jul 1, 2025(actual)
Construction end
Apr 30, 2029(forecast)

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65694 in the federal list. How to read these figures.