Schedule
Announced and approvedDec 16, 2022
today
2023202520272029
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- New Brunswick Community College
- Construction start
- Jul 1, 2025(actual)
- Construction end
- Apr 30, 2029(forecast)